冷冻干燥机验证计划
增加冷冻干燥机项目
Freeze-dryer Extension Project
Author:
Reviewed by:
Approved by:
Approved by:
SSPC WUXI
VALIDATION PLAN
Freeze Dryer
(GLZ 12)
…………………………………… Xin Juxaing, Validation Team Leader
…………………………………… Bertil Boman/Lu Xiaoan, Project Managers
…………………………………… Chen Yueyun, Production Manager
…………………………………… Ma Tao, QA Manager
Freeze Drying System
冷冻干燥机验证计划
Freeze-dryers Extension Project
增加冷冻干燥机项目
List of Contents
Page
1
INTRODUCTION ....................................................................................................................... 2
2
BACKGROUND .......................................................................................................................... 3
3
BRIEF DESCRIPTION OF THE FREEZE DRYER .............................................................. 3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
3.10
3.11
3
CHAMBER
DOORS ...................................................................................................................................... 3
PRODUCT
SHELVES ................................................................................................................................... 3
HEAT
TRANSFERRING
UNIT ...................................................................................................................... 4
ICE
CONDENSER ........................................................................................................................................ 4
MAIN
VALVE ............................................................................................................................................. 4
VACUUM
4
REFRIGERATING
UNIT ............................................................................................................................... 4
HYDRAULIC
STOPPERING ......................................................................................................................... 4
CIP
&
SIP
SYSTEM ................................................................................................................................ 4
CONTROL
SYSTEM ................................................................................................................................. 5
4
SCOPE .......................................................................................................................................... 5
5
VALIDATION TEAM ................................................................................................................ 5
6
INSTALLATION QUALIFICATION ...................................................................................... 6
6.1
6.2
6.3
6.4
CHECK OF THE
P&ID
6
CALIBRATION OF THE
INSTRUMENTS ....................................................................................................... 6
CHECK OF
UTILITIES ................................................................................................................................. 6
DOCUMENTATION ..................................................................................................................................... 6
7
OPERATION AND PERFORMANCE QUALIFICATION .................................................. 6
7.1
7.2
7.3
7.4
7.5
7.6
7.7
7.8
LEAKING
RATE
CHECK ............................................................................................................................. 6
HEAT
DISTRIBUTION
TEST ........................................................................................................................ 6
CIP
TEST .................................................................................................................................................... 6
SIP
TEST .................................................................................................................................................... 6
CAPACITY BY
WATER
TEST ...................................................................................................................... 6
SEALING
CHECKING
AFTER
STOPPERING ................................................................................................ 6
FREEZE
DRYING
CYCLE
TEST .................................................................................................................. 6
PLACEBO
PROCESS
VALIDATION
(ONLY
VITAMIN
C
+
GLYCINE
) ........................................................ 6
8
PRODUCT VERIFICATION .................................................................................................... 7
8.1
PRODUCTION
VALIDTION ......................................................................................................................... 7
9
APPENDIX .................................................................................................................................. 7
1 Introduction概述
This Validation Plan (VP) describes the validation intentions for the Freeze Drying machine at the facility of
Page 2 of
7
15 November 2010
Freeze Drying System
冷冻干燥机验证计划
Freeze-dryers Extension Project
增加冷冻干燥机项目
SSPC SVP Freeze Dryer Extension Project, as described in Validation Master Plan 400-VMP-P1. It is written
to cover the validation requirements and includes a description of the equipment, process and key functions.
There are two sets freeze dryers of type GLZ-12, made by Beijing Tianli Cryogenic Process Equipment Co.
Led will be introduced during freeze dryer extension project. Validation work will be performed separated
and there will be validation document number respectively, which is the binder No. 402 and 403.
This VP covers the product of Soluvit N.
A specific Validation Team, has been formed to co-ordinate the joint validation work carried out by the
existing plant.
A rough description of the planned tests is described with a time table.
2 Background背景
The process takes place on the first floor in hygienic class B area. The water solution of Vitamin is freezed
first. Then the ice is sublimated under very high vacuum during the drying steps.
The whole freeze drying process is controlled by a computerised control system.
The validation work for the freeze dryer covers all the process that including of the main steps as below:
--IQ and OQ
--Media & product filling
--Cassette transfer and loading and unloading
--Freeze-drying process including freezing, primary drying, second drying, pressure rise test, filling N2,
stoppering device
--Defrosting
--CIP & SIP
3 Brief Description of the Freeze Dryer冷干机简述
The freeze-dryers will be equipped, which type of GLZ-12 mainly consists of the following units:
3.1 Chamber腔室
The chamber is a welded fabrication of rectangular section manufactured from AISI 316L stainless steel
optimized to provided adequate access to components within the chamber whilst minimizing dead volumes.
The internal corners of the chamber have a radius >30 mm, a validation flange is fitted to the top of the
chamber.
3.2 Chamber Doors腔室门
The chamber main maintenance door is rectangular and fabricated from AISI 316 stainless steel. Hinged on
the left side when viewed form the machine room. There are two DN200 viewing windows mounted in the
door. A rectangular slot door is located on the opposite clean room side of the chamber to enable product to
be loaded.
3.3 Product Shelves 产品架
There are 9 product support shelves and one compensation (radiation) shelf in the chamber. Each shelf is
975mm wide X 1420 mm deep. The shelves, 24mm thick, are suspended vertically to create a stack with 110
15 November 2010
Page 3 of
7
Freeze Drying System
冷冻干燥机验证计划
Freeze-dryers Extension Project
增加冷冻干燥机项目
mm vertical clearance between each shelf.
3.4 Heat Transferring Unit 热交换单元
The circuit comprises a series of cooling and heating exchangers and circuit pumps. The medium passes
through shelves to effect heat transfer to the product. The temperature deviation between each shelves is±1℃. The capacity of this system may be cooled from +20℃ to -40℃ within 60 minutes without load and
heated at a rate of not less than 1℃/min.
3.5 Ice Condenser 冰凝结器
The cylindrical condenser vessel is mounted vertically behind the chamber. The vessel is fabricated from
AISI 316 stainless steel by a pair of dished ends welded to each end of a cylinder. There is manway of
400mm diameter on top of condenser. The total condensing surface area is 12.5 m2, providing a total capacity
for condensed ice of 240 kg. The refrigeration system provides sufficient capacity to the condense 240kg of
ice within 24 hours. Achieve an ultimate minimum temperature of –70℃ and cool the condenser from
+20℃ to -40℃ within 30 minutes.
3.6 Main Valve 主阀
The automatically actuated butterfly valve, which is fixed on the 400mm diameter vapour duct enable the
chamber and condenser to be isolated from one another.
3.7 Vacuum System 真空系统
The vacuum necessary for the freeze drying process is created by use of two 2-stage, oil sealed, rotary vane
pumps equipped with gas ballast and exhaust oil mist filters. The Pirani vacuum gauges that equipped at
main vacuum pipe and the chamber each will provide signals to vacuum measurement recording and control.
3.8 Refrigerating Unit 冷却单元
The three individual refrigeration circuits are configured to be able to serve either condenser or shelves
cooling duties as required during the various stages of the process.
3.9 Hydraulic Stoppering
A hydraulic cylinder is mounted above the chamber, it can provide with adjustment for stoppering pressure
and safety devices to prevent excessive force being generated. Operation of the hydraulic system is
interlocked to prevent the shelves being operated with the chamber door open.
3.10 CIP & SIP System
The CIP system comprised a series of self-draining, fixed and rotary spray nozzles mounted on the
distributing mainifolds positioned within the chamber and condenser. Some fixed nozzles and one rotary
nozzle are employed. The CIP process is initiated through the LyoManager control system and is operated
automatically by the PLC.
3 times pre-vacuum steam impulse process is employed during SIP. The chamber and condenser are designed
and fabricated as pressure vessels to enable sterilization of the temperature to be achieved 130℃. The SIP
process is initiated through the LyoManager control system and is operated automatically by the PLC. It is
base on the temperature of the chamber drain. When the sterilization finish, a water ring pump is use for
removal steam and moisture from the system. After this, nitrogen is filled until the pressure in the chamber
and condenser achieved to preset point.
15 November 2010
Page 4 of
7
Freeze Drying System
冷冻干燥机验证计划
Freeze-dryers Extension Project
增加冷冻干燥机项目
3.11 Control System 控制系统
The control system consists of a PC, control panel with a set of PLC, printer and recorder.
Vacuum sensors and temperature sensor are the main input process signal. (for further details, see Technical
Specification)
The general layout of freeze- dryer as below
注射用水纯蒸汽CIP罐液压系统N2过滤器N2真空计CIP泵去2号干燥机真空计冷凝室真空泵真空泵硅油箱冷冻水出冷冻水进硅油循环泵电加热器压缩机
4 Scope 范围
The purpose of this VP is to describe a study to determine whether the system as described in the
background:
satisfies the GMP requirements of the Regulatory Authorities: People’s Republic of China, the EU GMP
and internal standards of SSPC and Fresenius-Kabi.
is properly constructed, installed, operated and maintained.
is suitable for its intended use and capable of consistently producing products that meets their pre
determined specifications and quality attributes.
This VP covers the freeze-drying process of Soluvit N. Raw materials dispensing, formulation, vials washing
and sterilization, filling of solution are excluded, and because of they have been validated before and work
well for many years.
5 Validation Team
The Validation Team members will be from the following departments:
Validation Team member Responsibility
Project Group:
Bertil Boman
Lu Xiaoan
Project responsible
15 November 2010
Page 5 of
7
Freeze Drying System
冷冻干燥机验证计划
Freeze-dryers Extension Project
增加冷冻干燥机项目
Production Department:
Zhu Wei
Xu Hongliang
Xin Juxiang
Receiving department
QA representative
Validation Team leader
Quality Assurance:
Validation Group:
6 Installation Qualification 安装确认
These IQ tests will provide documented evidence that the equipment was installed to meet all cGMP, safety
requirements and technical specification. The IQ protocol was supplied and executed in local factory by
vender and SSPC technical staff together, and most tests are covered by the FAT document and IQ protocol.
Anyhow, the IQ protocol and test results should be reviewed by SSPC Validation Master Team, and some
tests will be added as below during re-assembling:
6.1 Check of the P&ID Drawing 检查流程图
6.2 Calibration of the Instruments 效核仪表
6.3 Check of Utilities 检查公用介质
6.4 Documentation 检查文件
7 Operation and Performance Qualification 运行与性能确认
These OQ tests will provide documented evidence that the equipment operated to meet all cGMP, safety and
designed specification. The OQ protocol was supplied and executed in local factory by vender and SSPC
technical staff together, and most tests are covered by the FAT document and OQ protocol. Anyhow, the OQ
protocol and test results should be reviewed by SSPC Validation Master Team, and some of the tests will be
re-executed as below during start up:
7.1 Leaking Rate Check 泄漏率检查
7.2 Heat Distribution Test 热分配试验
7.3 CIP Test 在线清洁试验
7.4 SIP Test 在线消毒试验
7.5 Capacity by Water Test
最大捕水能力测试
7.6 Sealing Checking After Stoppering 压盖后密封试验
7.7 Freeze Drying Cycle Test 冷干周期试验
7.8 Placebo Process Validation (only Vitamin C + Glycine
)
15 November 2010
Page 6 of
7
Freeze Drying System
冷冻干燥机验证计划
Freeze-dryers Extension Project
增加冷冻干燥机项目
8 Product Verification 产品验证
8.1 Production Validation
Test to verify that the correct quality attributes and requirements are fulfilled. It includes production of at
least three consecutive batches of the following:
“Soluvit N” Product
PV will additionally include verifying that the total processing up to a finished product fulfils the product
specification.
9 Appendix附录
Process Flow Drawing of Freeze Dryer
Production Process of “Soluvit N”
15 November 2010
Page 7 of
7 Appendix 9.1
Appendix 9.2